Dongguan Hui Yue Technology HY-R20 automatic machine wear bushing wear bushing installation mechanism for the production and use of contrast existing mode of production in the existing CNC winding machine, agency staff will use the copper wire to PIN foot Touchan and automatic loading and unloading of this time to specify the length of the sleeves cut off, and the copper casing head automatically put aside, artificial hanging at boot foot copper copper wire pulling his head had been wearing a sleeve, just Pull the hand at the same time positioning (This action takes less than 0.5S) at the sleeve can be used directly. The following Deng Hui workers more to tell you about our HY-R20 automatic wear bushing machine troubleshooting method
Automatic wear bushing machine troubleshooting
After boot steps:
Purging ------- check (double clamps inside the waste and clean) ----- ----- quit running
Abnormal work appears:
Purging ------ ------ exit examination (above) ---- ----- quit running
Blocking Teflon casing failure
1. The choice of feeding tube guide pin is too large, check and send the appropriate choice of the needle guide tube
2. Dual preload gap is too small or too large compacts, check and debug preload gap (Teflon casing can not pull from the side)
3. Dual briquetting closed open inflexible, spray WD-40 rust preventive oil in the square shaft at and clean with a blow gun
Blocking line failure
1. send wire-guided needle selection is too large, check whether it is reasonable to send wire-guided needle and replace reduce a type of nozzle
2. send wire-guided needle is too small to increase the choice of a model (copper barely passed)
3. sending wire wheel wear and replaced with new wheels, and transfer of small L crank the tension force
4. Teflon casing incision is not round, the replacement pipe cutting blade
5. send wire-guided needle and distance double briquetting is too large (both distance 0.1mm, please use our confirmation to the feeler distance)
Other faults
1. Motor vibration does not run: Check the data cable link or a direct replacement of the control box.
2. The back line no lines at the mouth plane: extended length delivery, sending wire wheel wear and replaced with new wheels. Check the clip wire line action is slow, slow to replace the control solenoid valve if the cramping into the line.
3. muffler noise during operation, check valve, replace thread cutter cylinder
4. The rest of the leak, check for loose fittings or replace stainless steel fittings
Precautions
1. Select the appropriate cannula guide pin and copper needle guide
2. The clear material, be sure to double-check and clean the waste briquetting and confirmation within double clamps tightly closed after launch operation
3. Pressure run more than 4.8 kg of pressure
4. Adjust the double clamps suitable preload height (depending on the different compacts Teflon tube height adjustment)
Source:HUITUE